Battery Bank.
Rating of batteries: 80AH, 220V generally for 132/33KV Level Sub-stations, 200AH to 250AH with 220V DC and above for 220/132KV voltage levels and above.
Fig: 220V, 200AH Battery set.
Importance of
batteries in EHT sub-stations: The batteries are used for protection
of the sub-station equipment from internal faults like Transformer internal
faults [Electrical Internal faults, Thermal faults of the Transformers] and
external faults like line faults [i.e earth fault, over load faults] and back
up protection of the equipment. The batteries are simply can say the heart of
the Sub-station, no electrical sub-station can be commissioned without batteries
along with charger. The batteries are using along with 3ø Ac/DC FC/BC Charger for
protection of the sub-station total
equipment from external and internal faults even in the condition of Station LT
supply to charger failed as batteries can feed DC sufficiently for 4 to 6hrs
with previous charging.
80AH to 250AH, EXIDE,
AMARRAJA, STANDARD, electroflo and Ub-Mech make batteries are used for all EHT
sub-stations..
Maintenance: The batteries should
be clean to avoid self discharge on [+ve terminal to –ve terminal].Inspection
of voltages, sp. Gravities, level of the float of battery and connection
between the battery terminals to avoid failure of DC as the batteries are
connected in series to obtain 220V DC.
Recently the VRLA
Maintenance free batteries are used for EHT Sub-Stations rather than Lead acid
cells. But the maintenance free battery
set makes an open circuit, if one of the cells in battery bank opens. This
leads to failing of the 220V DC supply to the protection system.[relays,
breakers of the Sub-station].
[precaution: 1]The protection of the sub-station
cannot be run with on 220V DC charger supply in the condition of battery DC
fails as no reliability of station Transformer LT 440V LT supply.
[precaution: 2]Even though continues availability
of the AC supply from station Transformer supply, the bus voltage of LV Bus
[33KV] may decreased suddenly due heavy fault current flow due to any external
fault simultaneously, the 3Ø LT AC voltage of station transformer out put falls
to a great extent and further the charger DC Output also decreases fails the
total protection of the sub-station.
Precaution: 3] No one battery or battery
bank should not allow short circuit and monitoring the DC leakage current [in
mA maximum of 50mA] of the battery bank. If dc leakage observed on either of
+ve or –ve terminal, should check out the leakage and disconnect the leakage
path in the load circuit.
The DC Leakage
circuit;
Sl. .No.
|
Particulars
|
Standard
|
Emco
|
Ub-mek
|
Electro flo
|
|||||
80AH
|
200AH
|
80AH
|
200AH
|
80AH
|
200AH
|
80AH
|
200AH
|
|||
A
|
Initial filling of the batteries
|
|||||||||
1
|
Electro lyte sp. Gravity
|
1.19 0 @27oC
|
1.19 0 @27oC
|
1.19 0 @27oC
|
1.19 0 @27oC
|
|||||
2
|
Soaking time
|
12 to 16hrs.
|
12 to 16hrs.
|
12 to 16hrs.
|
12 to 16hrs.
|
|||||
B
|
First charge
|
But not >24Hrs.
|
But not >24Hrs.
|
But not >24Hrs.
|
But not >24Hrs.
|
|||||
1
|
Initial charging duration
|
100Hrs.
|
80Hrs.
|
50Hrs.
|
100Hrs.
|
|||||
2
|
Rating of charging
|
4A for 60hrs.
|
10A for 60hrs.
|
3.2A for 10hrs.
|
8.0A for 80hrs.
|
6.0A for 50hrs.
|
15.0A for 50hrs.
|
4A for 60hrs.
|
10A for 60hrs.
|
|
Rest for 4Hrs.
|
--
|
Rest for 4Hrs.
|
||||||||
3.
|
4A for 40hrs.
|
10A for 40hrs.
|
4A for 40hrs.
|
10A for 40hrs.
|
||||||
4.
|
Maximum permissible temperatures
|
50oC
|
50oC
|
50oC
|
50oC
|
50oC
|
50oC
|
50oC
|
50oC
|
|
5.
|
During charging readings [Voltage]
|
2.55V
|
2.55
|
2.40
|
2.40
|
2.40
|
2.40
|
2.5
|
2.6
|
|
6.
|
At the end of the charging [Sp.Gravity @27oC ]
|
1200+0.05
|
1200+0.05
|
1200+0.05
|
1200+0.05
|
1200+0.05
|
1200+0.05
|
1200+0.05
|
1200+0.05
|
|
C]
|
Capacity
/discharge test
|
|||||||||
1
|
Discharge current
|
8A
|
20A
|
8A
|
20A
|
8A
|
20A
|
8A
|
20A
|
|
2
|
Test procedure :
|
After completion of the 1st charge, allow the battery to
stand on open circuit for not less than 12hrs. butnot more than 24Hrs.
discharge the battery through a variable resistor or acetated water load at constant current
equal to I=0.1C, the discharge shall be stopped when the closed circuit
voltage of each battery falls to 1.85V, and specific gravity falls to 1.130
obtained in the duration of 10Hrs, maximum.
|
||||||||
D]
|
Recharging
|
|||||||||
1.
|
Normal recharge
|
|||||||||
2.
|
Current and end voltage of the cell
|
8A up to 2.35V to 2.4V
|
20A up to 2.35V to 2.4V
|
11.2A up to 2.4V
|
28A up to 2.4V
|
8A up to
2.4V
|
20A up to
2.4V
|
8A up to
2.4V
|
20A up to
2.4V
|
|
3.
|
Finishing charge Current and end voltage per cell
|
4A up to 2.55V to 2.65V
|
10A up to 2.55V to 2.65V
|
5.6A up to
2.40 full Volts.
|
14A up to
2.40 full Volts.
|
4A up to full charge
|
10A up to full charge
|
4A up to
2.65V
|
10A up to 2.6V
|
|
4.
|
End sp.gravity of the cell at 270C
|
1.200+0.05
|
1.200+0.05
|
1.200+0.05
|
1.200+0.05
|
1.200+0.05
|
1.200+0.05
|
1.200+0.05
|
1.200+0.05
|
|
5.
|
Maximum charging range
|
12A
|
30A
|
16A
|
40A
|
18A
|
45A
|
12A
|
30A
|
Note:Temperature correction: if cell temperature is different form 270C, correction to specific gravity is to applied is 0.0007 per each Degree variation of the below or above the 270C
Maintenance
of the batteries:
a]
Keep the battery room dry and well ventilated.
b]
Keep the battery and its surrounding dry.
c]
Keep the battery top surface clean and dry forever.
d]
Ensure the tightness of the all battery connector erminals.
e]
All battery terminals should be cleaned and covered with thin layer of the petroleum
jelly.
f]
Traces of corrosion to be removed properly and to be cleaned the terminals with
distilled water.
g]
Metal kettles should not be used for topping up of distilled water to maintain
float level of the each battery.
h]
care to be taken when work with metal tools on battery bank to avert short
circuit of the battery terminals.
i]
When handling electrolyte or concentrated acid, safety measures to be taken like
wearing of apron and glows.
j]
like bare lights, smoking of cigarette which creates sparks should be avoided in the battery room.
Connected Battery
Charger:
k] very weak or discharged battery cells should be recharged separately to avert over charging of remaining batteries in the battery bank..
l] at least once in a 15 days,battery bank should be discharged [i.e kept off the float charger in the load condition of the battery bank] for 1:00 Hrs. to 1Hrs.:30Mins.
m] Check the each battery cell voltage and specific gravity in the load condition to ensure the healthiness of the each battery cell.
n] ensure the perfect continuity of the batteries by taking voltage of the each cell with voltmeter/multi meter from other adjacent cells terminals as below.
k] very weak or discharged battery cells should be recharged separately to avert over charging of remaining batteries in the battery bank..
l] at least once in a 15 days,battery bank should be discharged [i.e kept off the float charger in the load condition of the battery bank] for 1:00 Hrs. to 1Hrs.:30Mins.
m] Check the each battery cell voltage and specific gravity in the load condition to ensure the healthiness of the each battery cell.
n] ensure the perfect continuity of the batteries by taking voltage of the each cell with voltmeter/multi meter from other adjacent cells terminals as below.
The voltmeter connectors connected at +ve terminal of the 108th cell
and –ve terminal of the 100th Cell i.e the volt meter measures the
voltage of the 109th cell including voltage drop due to contact
resistances of connecting bars ‘a’, ‘b’
and internal resistance of the cell. If any loose contact between cells from
+ve of 108th cell to –ve of 100th cell, the voltmeter
shows above 2+0.02 V or abnormal voltage. Sometimes Heat dissipation may
be observed due to lose contact resistance I2R loss. The float
charger is to be kept on immediately to reduce the load on the battery bank and
tight the battery terminals with safety precautions. [i.e the float charger
feeds the load in especially in the cases of continues load of EHT sub-stations
protection and auxiliaries.
Distilled
water or demineralized water Topping up
Topping
up of Distilled water or de mineralized water [as per IS 1069] is necessary up
to sufficient level of float of each battery. Distilled water should not be
filled above the float red mark which leads to lower the specific gravity of
the battery cell.
Topping
up of Distilled water or demineralized water [as per IS 1069] is necessary up
to sufficient level of float of each batter is mostly suggestible just before
the battery bank boost charging.
Battery trouble
|
cause
|
Remedy
|
over charging
|
Excessive gassing and buckling of plates, filling
of active material on +ve plates, increasing of the temperature.
|
Reduce the float or boost charging voltage to a
value which attains the specific gravity of electrolyte is 1.200.
Or add distilled water if level is near or below
to red mark.
Ensure the accuracy of the voltmeter on FC/BC
charger if necessary to avoid over or low charging of the batterys.
|
Under charging
|
Low specific gravity of electrolyte,
Reversal of voltage, light colour plates, buckling
of the plates.
|
Put the battery bank in the boost condition which
increases the voltage 2.16 V to 2.2/each cell attains specific gravity 1.200
of electrolyte.
Carefully check leaking of the electrolyte from
cell if found arrest the same. Ensure that no earth leakage in the battery
circuit or load circuit in the field which lead unwanted discharging of the
battery bank.
|
Corrosion of the plates
|
Impure electrolyte
|
Disconnect the battery from the circuit, remove
the electrolyte, flush with distilled water and refill with fresh
electrolyte. Further separately charge the cell up to 1.200+0.005 specific
gravity and 2.00+5% V and reconnect the cell in the circuit.
|
Flaking of active mterial
|
Charging done at high rate, material impurity
applied on plates.
|
Charging and discharging limits should be limited
between 2.4V to 1.85V
|
Lose of voltage, battery voltage falls too on discharging
condition
|
Excessive sulphation, loose connections,
Corroded terminals.
|
sulphation at initial stage can be rectified by
low rate of repeated charging and discharging of the cells.
|
Continues lowering of the electrolyte level
|
Loss of water in the electrolyte due to evaporation
by too high float voltage or over charging.
Leakage of electrolyte.
|
Corroded parts should be cleaned with warm
distilled and cover with thin layer of patrollium gelly or vasaline.
Check and
arrest the leakage.
|
Over flowing of the electrolyte level even without the addition of the distilled water
|
Due to humid atmosphere in the battery room
causing condensation on the cell top surface.
|
Replace container incase of any leakage.
Improve ventilation in the battery room.
|
DC Chargers:
Main
Input AC supply is fed from AC Distribution Board-3h. 33KV/415V, 100KVA Station Transformer for 132/33KV sub-stations
connected to 33KV bus side and feeds to AC Distribution Board. The Float cum/Boost
Trickle Charger connected to 3Ø AC Supply on AC Distribution panel. The AC
supply converted in to 220V to 245V DC and feeds battery bank, relays and
auxiliaries. The Float cum boost 220V battery charger is very important to
maintain the batteries healthy charge condition. If the discharging time is
more during the line clears/interruptions on 33KV Bus or 33KV Station transformer,
the boost charger is used to boost the batteries up to good level i.e specific
gravity should be around 1.2+5% and voltage around 2.0 volts +
10% in next load condition. Example: FC/BC Charger Make: HEE 220V Dc, 200AH Float Current: 8 Amps, Boost Current: 16 Amps
Float charging: the charger
supplies 220V to 235V to load as well as batteries to light charging to hold
full charge [i.e compensate to self discharge and backup during protection
operated times]. The charging current is order of 0.2A to 0.5A only.
Boost Charger: the charger is
utilized for boost the batteries by supplying 235V to 290V DC, current is maximum
of 8A for 80AH batteries and 20A for 200AH batteries. During the boost
charging, the entire battery set doesn’t connect across the load as the boost
voltage more than system operating voltage i.e >220+10%. It causes
failure of protective relays, contractors, and trip, close coils in the
breakers. Hence the load is connected from 1to84th cell of the
battery bank to reduce the load voltage up to rated voltage. Entire battery
bank connected to boost charger to obtain full charging with DC voltage from
235V to 290V.
I like this post. Thanks for sharing this post. Keep sharing more posts like this! Construction company in the Philippines
ReplyDelete